A Valentine’s Present for Krasnow

This just in from our Design Build Contractor:
————————————————————————–

Mike,

Whiting-Turner is very excited to mobilize to the site in anticipation
of starting construction in the next few weeks. Below is a list of
activities that will be happening starting Tuesday February 14 and
continuing for the next two weeks:

1) Temporary site security fence delivered and installed
2) Construction dumpster delivered and placed
3) Construction gate installed
4) WT trailers will be delivered and installed
5) Temporary power, data, phones installed to trailer
6) Temporary toilet facilities placed on site
7) Tree selection and identification for future clearing activities

These activities will require that a few of the staff, faculty and
students of Krasnow to alter their current parking and walking habits.
There will not be any parking or access to the rear of the Krasnow
Institute unless in an emergency.

Jim Jaco will be on site Monday to work on laying out the specific areas
and identifying site fence boundaries. WT will work with Siemens to
coordinate with their site logistics.

Thanks,

Scott McEntee
Project Manager