MRI update

Here’s the latest information based on this morning’s teleconference
with the Siemens team. The installation is most likely to begin in
the first week in February. We’re looking at ten weeks. And the
magnet delivery date is right now scheduled as April 24/25.

Joining me on the director’s blog over the next months will be Mike Herman who is our project engineer/coordinator at GMU Facilities Planning and Dr. Layne Kalbfleisch (who has been a guest commentator before)–Layne co-heads up our Neuroimaging Core with Dr. Kevin McCabe. This will be the location for all information regarding construction/installation projects.

Welcome Mike and welcome back Layne…

Jim